De Soto weighs two more data center projects, with a planning vote set for Tuesday
The Daily Olathe team
If you drive K-10 near De Soto, more data centers may be coming. Planning commissioners are scheduled to vote Tuesday on a recommendation for phase two of Beale Infrastructure's campus: two more buildings, about 865,000 square feet each. The city council must approve the site plan before phase two can move forward.
Commissioners put the vote off on Oct. 27 to give city staff time to address several issues, including access from 95th Street, rooftop noise barriers and concerns with the fourth building. The fourth building, at W. 95th Street and Edgerton Road, is about 250 feet from the nearest residence. A noise study puts the loudest level at a nearby home at about 49 decibels.
Projected noise at a nearby home falls just under the nighttime limit
49 dBALoudest projected level at a nearby residence
Source: Lawrence Journal-World
View as table
| Value | |
|---|---|
| Loudest projected level at a nearby residence | 49 dBA |
| Nighttime limit | 50 dBA |
Next door, De Soto leaders delayed a decision last Thursday on Digital Realty's proposed $7.5 billion campus near the Panasonic battery plant. Council members said they wanted more time to review the development agreement and its tax incentives.
Digital Realty's Astra North campus, by the numbers
- $7.5 billion
- proposed cost of the data center campus
- 274 acres
- in the plans, out of about 1,435 purchased
- 600+ MW
- of electricity expected, with a maximum load near 675
- $6 million
- a year in city sales tax once both buildings operate
Source: tonganoxiemirror.com
- Beale site: 288 acres at 38000 W. 103rd St.
- Beale phase two: more than 1.7 million square feet
- Beale parking: 200 spaces per building
- Astra North city fees: about $6.19 million when fully built
Sources: Lawrence Journal-World, tonganoxiemirror.com